The following dc portion of a PV schematic (functionally grounded conductor not shown) is submitted to the building official for permit approval. The building official, who also is he AHJ, allow the system to be installed by requiring what NEC-required MINIMUM size equipment grounding conductor at Location A?
A residential PV system uses two 120.240Vac utility-interactive inverters with a sealed lead-acid battery
energy backup for protected loads. The MOST important protected load consideration when operating in the
backup mode is that:
A homeowner is weighing the PV module options for a roof-mounted solar array. Which is a correct option to
present to the homeowner?
A customer has a 200A service with a 200A rated panel and 200A main breaker located on the street side of
the house. There is a 100A breaker located at the opposite end of busbar feeding a 125A subpanel in the
backyard. The customer would like to place the inverter the backyard and use the 125 subpanel. Which
MAXIMUM inverter(s) output circuit current could be installed?
A project is using a PV module with a 25-38dc maximum power voltage range and a single input inverter with
an operating windows of 250vdc-450dc. The dwelling the system is to be installed on has a 5:12 roof with a
southeastem face that can accommodate 14 modules and southwestern face that can accommodate 10 modules.
What is the MAXIMUM number of modules that can be installed for proper inverter maximum power point