×

Special Offer! Limited-Time Offer! Get 25% Off on All Certification Exams – Prepare & Pass with Confidence! Use Code:  DC25OFF  

Free PMI PMI-SP Exam Questions

Try our Free Demo Practice Tests for Comprehensive PMI-SP Exam Preparation

  • PMI PMI-SP Exam Questions
  • Provided By: PMI
  • Exam: PMI Scheduling Professional
  • Certification: PMI SP
  • Total Questions: 325
  • Updated On: Jun 05, 2025
  • Rated: 4.9 |
  • Online Users: 650
Page No. 1 of 65
Add To Cart
  • Question 1
    • Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule? 

      Answer: C
  • Question 2
    • Mark is the project manager of the NHQ Project. Mark wants to create a salience model as part of his communications planning and scheduling. What does a salience model do for a project? 

      Answer: A
  • Question 3
    • Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

      Answer: D
  • Question 4
    • John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

      3

      Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days? 

      Answer: A
  • Question 5
    • You work as a scheduler for your organization. You are developing a schedule and its constraints for the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT an input to the schedule development process?

      Answer: A
PAGE: 1 - 65
Add To Cart

© Copyrights Dumpscity 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the Dumpscity.