×

Special Offer! Limited-Time Offer! Get 25% Off on All Certification Exams – Prepare & Pass with Confidence! Use Code:  DC25OFF  

Free PMI PMI-CP Exam Questions

Try our Free Demo Practice Tests for Comprehensive PMI-CP Exam Preparation

  • PMI PMI-CP Exam Questions
  • Provided By: PMI
  • Exam: Construction Professional in Built Environment Projects
  • Certification: PMI Built Environment
  • Total Questions: 60
  • Updated On: Jun 03, 2025
  • Rated: 4.9 |
  • Online Users: 120
Page No. 1 of 12
Add To Cart
  • Question 1
    • A construction professional is leading the construction of a new hospital. The project is halfway through its scheduled time frame. The construction professional monitors the scope along with other project constraints, and thinks that, overall, the project seems to be on track. However, some key stakeholders are concerned about potential cost overruns.

      What can the construction professional do to address the stakeholders' concerns?


      Answer: B
  • Question 2
    • A senior construction professional works on a nuclear power plant which will be planned and executed using the Advanced work packaging (AWP) approach. After the definition of construction work areas (CWAs), the construction professional moved on to the preparation for the workface planning phase. One of the project planning team wondered about the relationship between the Engineering Work Packages (EWP), the Construction Work Packages (CWP), and the Installation Work Packages (IWP).

      What should the construction professional’s answer be? (Select two)


      Answer: A,D
  • Question 3
    • A construction professional decides to use the PDRI tool throughout the Front End Planning (FEP) process. The construction professional defined four assessment points: after the feasibility study, after the concept phase, during the detailed scope phase, and at the end of the FEP phase.

      How will the PDRI score typically evolve through these assessment points?


      Answer: B
  • Question 4
    • An organization is running a construction megaproject with over 100 interfaces. As it faced some issues in IM implementation, the organization requested the advice of a senior construction professional. After assessing the existing IM implementation, the construction professional recommended the organization to set up a single centralized document to easily review the status of all Interface Agreements (IA).

      What document does the construction professional refer to?


      Answer: C
  • Question 5
    • To properly manage interfaces, a general contractor defined the roles and responsibilities of stakeholders involved in all interface points (IPs). For instance, a construction professional is assigned to develop, implement, and manage the Interface Management Plan (IMP).

      What is the role of the construction professional?


      Answer: B
PAGE: 1 - 12
Add To Cart

© Copyrights Dumpscity 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the Dumpscity.