×

Special Offer! Limited-Time Offer! Get 25% Off on All Certification Exams – Prepare & Pass with Confidence! Use Code:  DC25OFF  

Free PMI PMI-ACP Exam Questions

Try our Free Demo Practice Tests for Comprehensive PMI-ACP Exam Preparation

  • PMI PMI-ACP Exam Questions
  • Provided By: PMI
  • Exam: PMI Agile Certified Practitioner
  • Certification: PMI ACP
  • Total Questions: 492
  • Updated On: Jun 05, 2025
  • Rated: 4.9 |
  • Online Users: 984
Page No. 1 of 99
Add To Cart
  • Question 1
    • During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do? 

      Answer: A
  • Question 2
    • An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

      Answer: A
  • Question 3
    • Iterations last between a couple of weeks to a couple of months, with a preference for the shorter time. What is the goal for each iteration? 

      Answer: B
  • Question 4
    • A team member on a new scrum project previously provided support to another application Due to issues with that application, the team member's former supervisor continues assigning them tasks related to that project. The new project's scrum master includes this issue in the risk register. What should the scrum master do next?

      Answer: D
  • Question 5
    • During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do? 

      Answer: A
PAGE: 1 - 99
Add To Cart

© Copyrights Dumpscity 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the Dumpscity.