A manufacturing company uses Dynamics 365 Supply Chain Management.
The company replaced its burners to limit carbon dioxide emissions. The new burners require frequent
servicing to be compliant with environmental regulations. The new burners ate more complex and take longer
to service than the previous burners.
The production controller must track fuel use in liters to schedule timely maintenance. The additional time taken to plan maintenance must be considered.
You must configure the system to meet the requirements.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.