The interface GET_REFERENCE_DATE can be used to automatically derive dates for events in progress tracking. Which BAdl do you use to access this interface?
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question