Special Offer! Limited-Time Offer! Get 25% Off on All Certification Exams – Prepare & Pass with Confidence! Use Code:  DC25OFF  

Free iSQI CTAL-TM_Syll2012 Exam Questions

Try our Free Demo Practice Tests for Comprehensive CTAL-TM_Syll2012 Exam Preparation

  • iSQI CTAL-TM_Syll2012 Exam Questions
  • Provided By: iSQI
  • Exam: ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012]
  • Certification: iSQI
  • Total Questions: 65
  • Updated On: Jun 04, 2025
  • Rated: 4.9 |
  • Online Users: 130
Page No. 1 of 13
Add To Cart
  • Question 1
    • Testing Process
      Which of the following is an example of the test closure activity indicated as "lessons
      learned"?
      Number of correct responses: 1
      K2 1 credit

      Answer: C
  • Question 2
    • Test Management
      Which of the following statements, about the test reporting activities for a project adopting
      an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
      Number of correct responses: 1
      K2 1 credit

      Answer: D
  • Question 3
    • Test Management
      Based on the historical data of 5 past and similar projects, you have calculated these
      average numbers of defects detected in system testing:
      - for each 10000 LOC (lines of code), 200 defects
      - for each person-month of development team effort, 49 defects
      You want to use this information to perform estimation for a new project.
      The project manager tells you that he/she has estimated 20000 new LOC for this new
      project.
      Four developers work for four months on this project before system testing.
      During system testing, 797 defects are discovered.
      Assume that the system test of this new project is using the same amount of work as spent
      in the past projects.
      Based on this information only, which of the following statement is certainly true about this
      project?
      Number of correct responses: 1
      K3 3 credits

      Answer: B
  • Question 4
    • Test Management
      Consider an agile team adopting Extreme Programming (XP) with five developers and one
      tester without any coding experience.
      To which of the following activities would you expect the tester will contribute most?
      Number of correct responses: 1
      K2 1 credit

      Answer: D
  • Question 5
    • Topic 7, People Skills – Team Composition

      People Skills – Team Composition
      Which of the following would you expect to be most likely an example of a motivating factor
      for testers?
      Number of correct responses: 1
      K2 1 credit
       

      Answer: B