  • Question 1
    • In a manufacturing operation with the following annual cost structure, calculate the shutdown and break-even points as a percentage of total capacity.Fixed expenses: $5,203,440Variable expenses: $7,091,040Semi-variable expenses: $6,217,750Sales: $26,385,480Additional Information: Semi-variable expenses at zero production equal 30% of the expenses at full (100%) capacity.

      Answer: C
  • Question 2
    • Your company produces a wide variety of furniture, but you notice that many products share similar components or manufacturing steps. Which of the following philosophies would be most helpful in streamlining production by exploiting these similarities?

      Answer: A
  • Question 3
    • Given the project's status, how many hours have been earned if 6,573 hours have been spent and the project is 55% complete, against a planned 60%?

      Answer: D
  • Question 4
    • What is the appropriate course of action for a contractor when experiencing an inexcusable delay?

      Answer: A
  • Question 5
    • ____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.

      Answer: C